New Energy Code requirements don't slow down progressive, Washington-state-based UMC Inc.
C403.3.5 Dedicated outdoor air systems (DOAS). For buildings [with certain occupancy classifications], outdoor air shall be provided to each occupied space by a dedicated outdoor air system (DOAS) which delivers 100 percent outdoor air without requiring operation of the heating and cooling system fans for ventilation air delivery.
In some states, this new energy code requirement would create an uproar among HVAC contractors, but not in the state of Washington. Washington is known to have some of the most progressive energy efficiency building codes in the country. So, when the final version of the 2018 energy code included a requirement for DOAS, 麻豆入口 firms like Mukilteo, Washington-based UMC were prepared.
鈥淎s a design-build contractor with in-house engineering capabilities, UMC is actively involved in helping shape the direction of energy codes in our area,鈥 said Peter Boileau, UMC project executive/senior project manager. 鈥淜nowledge of not only what current energy code requirements are, but where future code requirements are going, is critical to advising our customers on the right HVAC system selections for their projects.鈥
A DOAS system uses a ventilation supply air fan and an exhaust/relief air fan. A heat exchanger between the two airsteams helps temper outside air to a neutral temperature.
Energy code expertise has been important to UMC鈥檚 work on a new 42-story building at 555 108th Street, NE, Bellevue, Washington 鈥 a suburban city seeing dramatic growth. When complete in 2023, the 600-foot office tower will be the tallest building by 150 feet in this high-tech city. Designed for occupancy by a single high-tech company, the building will be LEED certified and will also feature tailored systems designed to allow employees to do their best work in comfortable environments. DOAS systems will enable building users to experience the fresh, natural breeze of outside air.
鈥淥ur Bellevue office tower project was especially interesting in that the building qualified for the earlier 2015 energy code that did not require DOAS,鈥 Boileau said. 鈥淲ith our help the developer decided to build a code-forward building incorporating DOAS as they believed it would attract long-term 鈥榞reen鈥 tenants, and they were right.鈥
At nearly one million square feet and 600-feet-tall, the 555 tower is the first high-rise built under Bellevue鈥檚 new zoning for taller building heights. With 42 stories above grade and 980,000 square feet of shell and core office space, UMC is providing HVAC and plumbing design-build preconstruction and construction services, including detailing and coordination, manufacturing, garage systems, and a 2,000-ton capacity central cooling plant.
Rendering courtesy of NBBJ
According to Boileau, one DOAS unit will be installed on each floor of the Bellevue tower. A DOAS system typically provides a ventilation supply air fan and an exhaust/relief air fan, with a heat exchanger between the two airstreams to temper outside air to a neutral temperature of around 70 degrees F. The units on the 555 108th Street project are sized to provide minimum code required ventilation per floor occupant, plus 30% extra capacity to provide increased outside air 鈥榝lushing鈥 if needed. The installed DOAS units supply outside air for ventilation, exhaust for the building restrooms and relief air to maintain building pressurization requirements. The energy recovery heat exchanger pre-heats outside air in the winter and pre-cools it in the summer, which means no new energy is required to handle ventilation loads in the building, a significant reduction in energy use. DOAS units can be incorporated into smoke control/life safety systems if appropriate for life safety code compliance on high-rise buildings. They can also be used to offset high-rise 鈥渟tack effect鈥 in tall buildings located in cold climate regions, a strategy that was used in the 555 108th Street project.
The 555 108th Street development consists of a 5-story underground parking garage, a 42-story tower, and a retail/restaurant pavilion sharing a common outdoor plaza space. The mechanical system includes a 2,000-ton central plant which provides cooling to a distributed fan coil system. Perimeter heat is provided by electric resistance coils, with no heating required for interior spaces which is typical of buildings of this type constructed in Western Washington.
鈥淯sing DOAS on your building decouples the ventilation system from the thermal comfort system which maintains indoor temperatures,鈥 Boileau explained. 鈥淒OAS systems can, however, assist certain thermal comfort systems depending on the system selected. An example of this is the use of chilled beams or sensible-cooling only VAV systems. Since these systems cannot remove latent heat from the spaces they serve, the DOAS unit can be used to do this utilizing heat recovery and in some cases with additional pre-cooling coils to absorb latent heat and humidity as needed.
Boileau said Washington鈥檚 target is to reduce energy consumption on new residential and commercial buildings from 2006 code levels by 70% by 2031. This ambitious goal means an average of a 14% reduction for each code update compared to the previous code鈥檚 requirements to meet the 70% energy reduction target.
鈥淚n our state, we have optimized envelope, lighting systems and equipment efficiencies to reduce energy,鈥 he continued. 鈥淎 current focus is to limit the use of large, central fan systems to reduce overall fan motor energy use. This lines up with the increased use of DOAS and small/distributed thermal comfort systems we are currently seeing in our market.鈥
鈥淲here states do not subscribe to progressive energy codes, contractors are probably not installing DOAS because first costs are typically higher than traditional systems,鈥 said Boileau.
UMC President Steve Brooks agrees with this statement and believes this is a unique market. 鈥淒evelopers are spending more to comply with codes that reduce energy use and the carbon footprint of a building. Tenants want to be in a building that shares these goals.鈥
The future of energy codes in Washington State could include the elimination of both natural gas and electric resistance for heating buildings. Refrigerant based systems, including heat recovery chillers, heat pump boilers, and variable refrigerant flow (VRF) systems will be the 鈥榞o-to鈥 systems for future code compliance in the state.
Published: February 28, 2022
IN THIS ISSUE
Fabricating copper shingles helps to revive an historical dome in Vancouver.
In the second session of the 117th Congress, 麻豆入口鈥檚 Capitol Hill office will be working to build on the many important wins from 2021.
An ideal labor management partnership boosts JATC best practices
New Horizons guide offers tips on making the process smoother and easier
Employees are your greatest assets, particularly now as we emerge from the COVID-19 pandemic, and there鈥檚 even more turmoil and turnover across industries.
New Energy Code requirements don't slow down progressive, Washington-state-based UMC Inc.
Residential HVAC contractors are missing out on the high performance and profits the technology offers, manufacturers say
Grassi surveyed contractors and subcontractors to gauge the industry鈥檚 current condition and outlook
Specialized ductwork experience enables Black & McDonald to complete a complex industrial installation
We all know our training centers offer apprentices the opportunity to learn new skills and techniques in a classroom setting augmented by time in the contractor鈥檚 shop and/or field.