Poynter Sheet Metal installed 213,000 pounds of ductwork in an underground tunnel as part of a project to prevent the release of hazardous wastewater into nearby rivers.
麻豆入口 member Poynter Sheet Metal was awarded a $2.3 million, three-year contract to install ductwork and rooftop HVAC units for the 240-foot tunnel. Above, Poynter employees work from a lift to position duct.
When severe rainstorms came through Fort Wayne, Indiana, water department officials were forced into an action they didn鈥檛 want to take: release sewage into the nearby Maumee and St. Marys rivers.
It was the only way to prevent stinky, hazardous wastewater from backing up into city homes and businesses.
But that emergency solution carried a high cost. Releasing untreated or minimally treated water polluted the rivers and damaged wildlife and the environment. That鈥檚 why the city of Fort Wayne OK鈥檇 spending $188 million to create an underground tunnel that will reduce the need to send sewage into the waterways around the city. The project involves digging two 240-foot-deep shafts that will connect to the tunnel. The tunnel will collect the sewage before a pump station sends it offsite for treatment.
In 2021, 麻豆入口 member Poynter Sheet Metal was awarded a $2.3 million, three-year contract to install ductwork and rooftop HVAC units for the 240-foot tunnel. Matt Hamilton, Poynter鈥檚 director of industrial services, said the Greenwood, Indiana-based contractor had worked on a similar project for the city of Indianapolis. For that project, Poynter worked with F.A. Wilhelm Construction Co., the same general contractor overseeing the Fort Wayne tunnel project.
鈥淪o they put the team that had done the project in Indianapolis (back) together,鈥 Hamilton says. 鈥淪o we could go to Fort Wayne and do it again for them.鈥
A birds-eye view of a shaft that connects to a tunnel 240 feet below the city of Fort Wayne, Indiana. The tunnel is part of a pump station that will reduce sewer overflows and the need to release sewage into the Maumee and St. Marys rivers.
Major industrial projects like the pump station tunnel are nothing unusual for Poynter, a $280-million fabrication and installation contractor that company officials like to say does 鈥渁ll things metal.鈥 With a mix of commercial, industrial and even architectural work, there are few types of projects the company doesn鈥檛 handle.
Working from 180 feet below
While the tunnel was dug 240 feet below the city, Hamilton and his crew of eight sheet metal workers were mostly working from a higher operating deck about 180 feet down. That鈥檚 where most of the duct was to be installed. Besides ductwork, the contract called for Poynter to put in place hangers, grilles, registers and diffusers, two rooftop HVAC units, and exhaust fans.
Coordination and shop drawings were done in August 2021. Poynter Sheet Metal workers fabricated 213,000 pounds of 16-gauge rectangular ductwork for the tunnel and pump station at the company鈥檚 Greenwood facility, then hauled it three hours away to the construction site. Duct installation started in May 2023, taking about 10 months.
鈥淎nd we tried to put together multiple sections of duct to fill a semi trailer,鈥 Hamilton says. 鈥淪o it went up as one 50-foot-long piece. And then everything had to be hoisted into place and dropped down a shaft by a crane. We were able to stage multiple sections and then throughout the day send pieces down into the shaft.鈥
The access shaft was about 18 feet in diameter. Getting people and ductwork down there meant Poynter workers were in a lift with the duct sitting in a crane basket. 鈥淪o the only place you could do ground work or work out of a lift was when you were on the operating level,鈥 he adds.
Safety was key
Hamilton says that safely working with the lifts and cranes 鈥 alongside other trades 鈥 was one of the project鈥檚 major challenges. No one wanted any accidents.
Another look down into the 18-foot-diameter shaft that connects to a tunnel 240 feet below ground. The tunnel is part of a system to prevent having to release sewage into area waterways after storms.
鈥淲e were in constant communication with crane operators, making sure our guys were safe and had authorization to be swinging loads over the shaft,鈥 he says. 鈥淚t takes a lot of coordination and safety planning. Knowing our guys talking on a radio couldn鈥檛 see the crane operator, we had to be cautious.鈥
That meant starting each day with a job safety analysis. 鈥淚t was really critical to have a good lift plan for each day 鈥 to make sure we knew what were activities for the day, who we were communicating with, and make sure that nobody got caught in a bad spot since we're hanging off the end of a crane,鈥 Hamilton says.
Since the ductwork was being installed in a wet environment, the carbon steel duct hangers and reinforcements required a Tnemec coating to resist rust and wear.
鈥淭here鈥檚 water and moisture everywhere. It鈥檚 always going to be exposed to moisture,鈥 Hamilton says. 鈥淭he ductwork鈥檚 galvanized coating met the spec, so we didn鈥檛 have to spray it.鈥
Hamilton says the 鈥渞ooftop鈥 HVAC that the pump station ductwork feeds into isn't actually on a roof at all. They鈥檙e on concrete slabs, sitting at ground level above the tunnels. 鈥淵ou could just walk right up to the air handlers and then the ductwork all goes down into the vertical shaft,鈥 he explains. They supply 92,000 cfm of air in the tunnel to ensure workers鈥 safety and comfort.
The pump station project is almost finished. Poynter completed its work in March. When it鈥檚 operational, the system will reduce the need to release sewage into the rivers 鈥 from about 70 times a year to only four, officials say.
Published: August 26, 2024
IN THIS ISSUE
McClure Co. brings its healthcare facility expertise to Penn Highlands State College Hospital and Medical Office Building.
Poynter Sheet Metal installed 213,000 pounds of ductwork in an underground tunnel as part of a project to prevent the release of hazardous wastewater into nearby rivers.
Collaboration with labor partners, creating opportunities for members, and addressing the workforce challenges of the future are some of the featured topics in this sitdown with 麻豆入口's head.
Culture of Respect (formerly BE4ALL, Belonging and Excellence for All) launched in December 2021.
One of the core parts of 麻豆入口's mandate is to educate our member contractors on the evolving landscape of our industry.
Mentorships can nurture talent and strengthen your sheet metal and HVAC business.
Canadian 麻豆入口 contractor Heather & Little brings back the shine to a historic house from Hollywood鈥檚 golden age.
Construction and A&E industries show optimism and resilience in 2024.
Believe it or not, we are already preparing for the 麻豆入口 Annual Convention in Palm Desert, California.
New editions offer important updates to help 麻豆入口 contractors advance their knowledge.
麻豆入口 applauds the final rule issued by the Biden Administration that is designed to address the skilled workforce crisis shortage by requiring private developers to comply with Project Labor Agreements (PLAs) and Prevailing Wage and Apprenticeship
New agreement between organizations designed to develop and expand best practices, safety standards and encourage technological advancements across the entire union construction space.
On June 28, the U.S. Supreme Court issued a decision that will have far-reaching consequences for federal agencies. Specifically, in Loper Bright Enterprises v. Raimondo, the Supreme Court ended four decades of deference to federal agencies鈥 leeway
A 2024 market report highlights growing opportunity in the residential HVAC sector. Veterans HVAC Owner David Giacalone addresses energy efficiency, regulatory requirements and consumers鈥 demand for high-end systems.
Welcome New 麻豆入口 Members