With NHL and NBA season looming, Wells Fargo Center and StructureTone Construction Management turned to Ernest D. Menold, Inc. to build drink rails, bar supports and architectural frames for the Wells Fargo Center鈥檚 grand opening of the 鈥淣ew City Terrace.鈥 An addition to the scope of work included monitor supports and beverage racks above the new Bud Light Zone Bars under aggressive timelines and complicated structural issues, the crew at Ernest D. Menold, Inc. made the owners, and most importantly, the sports fans happy.
The project involved demolishing private boxes in the arena鈥檚 top level to create an open gathering space, called the Philadelphia Assembly Room, complete with bars, televisions and fireplaces. Ernest D. Menold, Inc., (Lester, Pa.), was awarded the opportunity to build the drink rails that run around the entire perimeter, the frames around the fireplaces, and other architectural items. The work performed this summer was part of a $250M renovation to the arena.
The contractor fabricated 45 individual powder-coated steel drink rail sections of various lengths, totalling 560鈥 of fixed drink rails, along with an additional 13 sections of removable rails to ensure American Disabilities Act (ADA) compliance. The design included a 3/8鈥 plate, a 1 1/2鈥 diameter schedule 40-pipe footrest, and a 4鈥6鈥 high stand with a granite top (built by another company). It involved 506 hours of shop fabrication and 396 hours of field installation (see image).
Though the sheet metal contractor has constructed similar rails, company president Ernest J. Menold points out this project was slightly different. 鈥淚t was a very aggressive schedule. It had to be done during the summer. Our work was some of the last work that went in, and it had to be ready for the beginning of the Flyers and 76ers seasons.鈥
Partway through the installation of the railing system, they were approached to do the Bud Light Zone Bars. This work was on an even tighter timeline. Says Menold, 鈥淲e got it at the end of July, so we had to be done in four weeks. That included helping the construction manager find a way to anchor these up into the building steel. We had to hire a structural engineer to approve our methods. This project was very, very aggressive.鈥
Though the team was a bit concerned by the number of uncertainties, they were also confident in their ability to complete the project. Menold points out, 鈥淲e have a reputation of being problem solvers, so a lot of our customers bring us in to help solve their problems. And Wells Fargo is one of those customers.鈥
The Bud Light Zone Bars consisted of racks with four shelves made with 16 gage shelf supports for glass to be laid in. The frames are 1 x 1 x 1/8鈥 steel tubes with 2 x 2 x 3/16鈥 steel wire mesh. Twelve framed openings allowed for mounting of television monitors (see image). Almost half of the 956 hours of shop fabrication were overtime, as were approximately one third of the 430 hours of field installation.
The team solved the challenge of fastening the bars by installing steel supports beneath the house steel of the Wells Fargo Center with the assistance of the structural engineer.
Menold notes that the finished project is something special for his coworkers. 鈥淭hey have great pride in the fact that this project is something that so many people can see. Not many people know that we did it, but it鈥檚 something they can point to and say, 鈥業 built that. for Wells Fargo.鈥 A lot of our work, especially HVAC, we don鈥檛 get an opportunity to see after it鈥檚 installed. It鈥檚 usually up behind a ceiling.鈥
Ernest D. Menhold recognizes the uniqueness of the project. 鈥淚t鈥檚 a custom fabrication. It鈥檚 probably not something we鈥檒l make again, but it鈥檚 nice to know we completed it on time and on schedule for our customer.鈥
Published: December 20, 2019
IN THIS ISSUE
Sheet metal and air conditioning contractors from across the United States gathered in Austin, Texas, from Oct. 20-23 to celebrate the 75th Anniversary of 麻豆入口 and to get the latest updates on economic, technology and construction industry trends.
At C&C Sheet Metal in Indianapolis, a successful 50 years has been a result of valuing both their employees and customers on a personal level.
Bel-Aire Mechanical expanded manufacturing capabilities at a Phoenix, Ari. medical technology manufacturing facility.
Stromberg, a 麻豆入口 firm based in Beltsville, Md, fabricated and installed duct systems at the International Spy Museum.
As temperatures drop around the country, people are starting to crank up the heat on their thermostats and break out their favorite cold-weather remedies.
Despite repeated attempts, the city鈥檚 union-affiliated sheet metal contractors held firm that they should be bound as an organization.
New 麻豆入口 president Angie Simon comments on recent milestones and on the impressions she hopes to leave during her year as president.
Austin, Texas attracted almost 1,000 members to 麻豆入口鈥檚 2019 annual convention. The event included experts speaking on the trends and issues affecting most affecting contractors today
It is important to make sure that multiemployer reform proposals are set up to protect contributing employers, the industry, and the multiemployer system.
How do you correct inefficient or controlling leadership behaviors? Self-awareness is the key.